S. Alamo Street and Drainage Improvements

Project Scope | Project Updates | Project Timeline | Project Contact | Alternate Routes

South Alamo Street Photo

Project Scope
The City of San Antonio's Department of Public Works, in partnership with the Bexar County Department of Public Works and San Antonio River Authority (SARA) are working in a collaborative manner with San Antonio Water Systems, CPS Energy and AT&T to improve the street condition and drainage facilities along S. Alamo Street from Probandt Street to Pereida Street. The proposed improvements will alleviate drainage issues along this corridor, improve roadway conditions, and provide enhanced pedestrian facilities. Construction began October 2012 and is estimated to be complete by August 2014.

Improvements include:

  • Roadway reconstruction from existing 4-lane to proposed 3-lane including a center turn lane
  • Improved drainage storm sewer infrastructure
  • Improved wider sidewalks:
    • 4 ft to 12 ft on the south side
    • 4 ft to 6 ft on the north side
  • Improved curb ramps to meet current ADA standards
  • Pedestrian crosswalks
  • Landscaping
  • Utility replacements:
    • SAWS water and sewer replacements including a 12-in water line and a 36-in sewer line under the San Antonio River
    • CPS underground gas main replacement
    • AT&T fiber optic line replacement

Project Updates

Timeline

CoSA-Public Works

SAWS

CPS Energy

AT&T

Oct 2012 – Dec 2012

 

Planned Scope:
Water: Install 12-in water main from Guenther to east bank of San Antonio River
Status: Complete

Planned Scope:
Gas: Install gas line form Probandt to west bank of San Antonio River. Continue gas construction from Guenther to Johnson
Status: Complete

 
Dec 2012 No construction during 2012 Holidays from December 21, 2012 to January 6, 2013. All barricades and signs will be removed from the street to allow full access along S Alamo during this time.
Status: Occurred
Jan 2013 Planned Scope:
Install storm sewer, curb inlets, manholes from east bank of San Antonio River to Guenther
Status: On-Going, 40% Complete
Planned Scope:
Water: begin water line utility adjustments for storm sewer from Guenther to Johnson.
Status: On-Going, 50% Complete
Planned Scope:
Gas: Install gas line form Johnson to Pereida.
Status: Complete
 
Feb 2013 Planned Scope:
Install storm sewer, curb inlets, manholes from east bank of San Antonio River to Guenther
Status: 80% Complete; Remaining Storm Sewer Segment Pending Completion of SAWS Phase II Sewer Siphon Installation
Planned Scope:
Sewer: Install 36-in sewer line from east bank of San Antonio River to Guenther. Install 10" sewer line from Guenther to Pereida.
Status: On-Hold Pending SAWS Contractor Availability
Water: Install water line utility adjustments for storm sewer from Guenther to Johnson.
Status: Complete
   
Mar 2013 Planned Scope:
Install storm sewer, curb inlets, manholes from Guenther to Pereida
Status: Complete
Planned Scope:
Water: Install water line utility adjustments for storm sewer from Johnson to Pereida.
Status: Complete
   
Apr 2013 No construction during month of April 2013 in observance of Fiesta Events. All barricades and signs will be removed from the street to allow full access along S Alamo during this time.
Status: Occurred

May 2013

No Activity Planned

Planned Scope:
Water: Install 12" water line from Guenther to Johnson.
Status: Complete

No Activity Planned

Planned Scope:
Relocating telephone utilities from Pereida to Johnson to provide access for drainage improvements
Status: Complete

June 2013 No Activity Planned Planned Scope:
Water: Install 12" water line from Johnson to Pereida.
Status: Complete
No Activity Planned Planned Scope:
Relocating telephone utilities from Johnson to Guenther to provide for drainage improvements
Status: Complete
July 2013 Planned Scope:
Install storm sewer, curb inlets, manholes from east side of San Antonio River to Guenther; Install storm sewer inlets at intersection of Guenther & S Alamo.
Status: On-Going, 80% Complete
Remaining Storm Sewer Segment Pending Completion of SAWS Sewer Siphon Installation.
No Activity Planned No Activity Planned Planned Scope:
Relocating telephone utilities from Pereida to Johnson to provide access for drainage improvements
Status: Not Started
August 2013 Planned Scope:
Install storm sewer, curb inlets, manholes from east side of San Antonio River to Guenther; Install storm sewer inlets at intersection of Guenther & S Alamo.
Status: Complete

Remove existing pavement and curbs, regrade street, and install new pavement along S Alamo from Guenther to Johnson Status: On-Going, 70% Complete
Preconstruction Meeting Scheduled for SAWS Sewer Siphon Installation:
Construction started Late August 2013
No Activity Planned Planned Scope:
Relocating telephone utilities from Pereida to Johnson to provide access for drainage improvements
Status: On-Going, 25% Complete
August 2013 thru Oct 2013 The intersection of S Alamo Street at Guenther Street will be closed for the months of August and October 2013. Vehicular access thru this intersection will not be allowed because of temporary sanitary sewer bypass pumping. Pedestrian access will still be available. Please use the internal traffic control detour located along Johnson Street and Wickes Street for traffic circulation thru the neighborhood.
Sept 2013 Planned Scope:
Install asphaltic base pavement at the S Alamo / Guenther Intersection
Status: Complete
Planned Scope:
SAWS Contractor to install dog-house manholes, begin bypass pumping, and install temporary 30" and 8" sewer lines between Probandt and Guenther.
Status: 90% Complete
No Activity Planned Planned Scope:
Relocating telephone utilities from Pereida to Johnson to provide access for drainage improvements
Status: Complete
Relocating telephone utilities from Johnson to Guenther to provide access for drainage improvements
Status: Complete
October 2013 Planned Scope:
Remove existing pavement and install new asphaltic base pavement between Pereida and Johnson
Status: On-hold pending SAWS adjustments of watermain, service lines, and sewer manhole along S Alamo Street
Remove existing curbs, sidewalks, and driveways between Pereida and Johnson
Status: On-hold pending SAWS adjustments of watermain, services lines, and sewer manhole along S Alamo Street
Planned Scope:
SAWS Contractor to continue bypass pumping and installation of temporary 30" and 8" sewer lines between Probandt to Guenther.
Status: Complete
Contractor to install shoring and begin excavating bore pit in preparation of sewer siphon work under the San Antonio River
Status: 5% Complete
Second SAWS contractor to perform watermain, service lines, and sewer manhole adjustments along S Alamo Street
Status: Complete
No Activity Planned No Activity Planned
November 2013 Planned Scope:
Remove existing pavement and install new asphaltic base pavement between Pereida and Johnson
Status: Complete
Remove existing curbs, sidewalks, and driveways between Pereida and Johnson
Status: On-Going, 60% Complete

Install new curbs, sidewalks, and driveways between Pereida and Johnson
Status: On-Going, 20% Complete
Planned Scope:
Contractor to continue excavating bore launching pit in preparation of sewer siphon work under the San Antonio River
Status: On-Going, 40% Complete

No Activity Planned No Activity Planned
December 2013 Planned Scope:
Remove existing curbs, sidewalks, and driveways between Pereida and Johnson
Status: On-Going, 90% Complete
Install new curbs, sidewalks, and driveways between Pereida and Johnson
Status: On-Going, 70% Complete
Install new curbs, sidewalks, and driveways between Johnson and Guenther
Status: Ongoing, 90% Complete
Planned Scope:
Contractor to continue excavating bore launching pit in preparation of sewer siphon work under the San Antonio River
Status: On-Going, 75%
No Activity Planned No Activity Planned
December 2013 S Alamo Street will temporary reopen from Pereida to Guenther starting Saturday, December 21 thru Sunday, January 5, 2014 for the 2013 Holiday Break. Starting Monday, January 6, 2014, S Alamo Street between Pereida to Guenther will be closed in order to resume construction work. S Alamo Street between Guenther and the San Antonio River will remain closed for SAWS construction work.
Status: Occurred
January 2014 Planned Scope:
Install new curbs and sidewalks between Pereida and Johnson
Status: On-Going, 85% Complete
Install new curbs and sidewalks between Adams and Wicks
Status: On-Going, 80% Complete
Install new curbs, sidewalks, and driveways between Johnson and Guenther
Status: On-Going, 95% Complete
Remove existing curbs, sidewalks, and driveways between Wicks and Guenther
Status: On-Going, 75% Complete
Install new curbs, sidewalks, and driveways between Wicks and Guenther
Status: On-Going, 30% Complete

Planned Scope:
Contractor to continue excavating north side bore pit in preparation of sewer siphon work under the San Antonio River
Status: Complete
Contractor to begin excavating south side bore pit in preparation of sewer siphon work under the San Antonio River.
Status: On-Going 3%

CPS Overhead:
Powerline adjustments to allow SAWS Contractor clear work zone on Bore Receiving Pit (south side bore pit) to begin on Jan. 16th. Approximate work duration: 1 to 2 weeks
Status: Upcoming
No Activity Planned
February 2014 Planned Scope:
Install new curbs and sidewalks between Pereida and Johnson
Status: Complete
Install new curbs and sidewalks between Adams and Wicks
Status: Complete
Install new curbs, sidewalks, and driveways between Johnson and Guenther
Status: Complete
Remove existing curbs, sidewalks, and driveways between Wicks and Guenther
Status: Complete
Install new curbs, sidewalks, and driveways between Wicks and Guenther
Status: Complete
Planned Scope:
Contractor to continue excavating south side bore pit in preparation of sewer siphon work under the San Antonio River.
Status: On-Going, 30% Complete

Contractor to begin boring under San Antonio River from north side bore pit
Status: On-Going, 15% Complete
CPS Overhead:
Powerline adjustments to allow SAWS Contractor clear work zone on Bore Receiving Pit (south side bore pit) to begin on Jan. 31st. Approximate work duration: 1 week.
Status: Complete
No Activity Planned
February 2014 S Alamo Street and Drainage Improvements Project Update Meeting scheduled for 6 pm on February 25, 2014 at Cliff Morton Development and Businesses Services Center located on 1901 South Alamo Street, 1st Floor Board Room. Staff will present the project improvements. Following the presentation, officials will be on hand to answer questions.
Status: Complete
March 2014 Planned Scope:
Install new curbs, curb ramps, and sidewalks at S Alamo and Guenther intersection
Status: Complete
Install 2" lift of Type "C" asphalt on S Alamo from curb returns at Guenther to Pereida
Status: Complete
Planned Scope:
Contractor to continue excavating south side bore pit in preparation of sewer siphon work under the San Antonio River.
Status: On-Going, 80% Complete
Contractor to continue boring under San Antonio River from north side bore pit
Status: On-Going, 55% Complete
Planned Scope:
Begin overhead electric pole adjustments along S Alamo from Guenther to Pereida
Status: Ongoing, 65% Complete
No Activity Planned
March 11, 2014 S Alamo Street from Pereida to Guenther is now substantially complete and open for traffic.
This segment is the majority of the City’s $2.4 M scope of work (total project value is $6.1 M), which has been completed by the City’s contractor, J3 Company, approximately six (6) weeks ahead of schedule. Please note the recently placed asphalt layer within this section is not the final pavement layer. J3 Company will install the final asphalt layer once the remaining scope of work between Guenther and Probandt is complete. The remaining section from Guenther to Probandt will continue to be closed until August to allow SAWS to complete construction of the sewer siphon system under the San Antonio River.
Status: Complete
April 2014 Planned Scope:
Install improved pavement surface at the intersection of S Alamo and Guenther
Status: Upcoming
See Notice Below.
Planned Scope:
Contractor to continue excavating south side bore pit in preparation of sewer siphon work under the San Antonio River.
Status: On-Going
Contractor to continue boring under San Antonio River from north side bore pit
Status: On-Going
Contractor to begin installing siphon piping on both bore pits
Status: Upcoming
Planned Scope:
Continue overhead electric pole adjustments along S Alamo from Guenther to Pereida
Status: On-Going
No Activity Planned
April 14, 2014 The intersection of S Alamo St. and Guenther St. will be closed to traffic on Monday, April 14, 2014, to enable the installation of an improved pavement surface. The intersection will reopen to traffic circulation on the morning of Tuesday, April 15, 2014.
Note: This activity has been postponed because of the rain experienced on this day. This activity has been rescheduled for Wednesday, April 16, 2014.
April 16, 2014 The intersection of S Alamo St. and Guenther St. will be closed to traffic on Wednesday, April 16, 2014, to enable the installation of an improved pavement surface. The intersection will reopen to traffic circulation on the morning of Thursday, April 17, 2014.

Note: Please check this web page for continuous timeline updates.

Project Contact
David Hook: Capital Project Officer (210) 207-8036