The Vertical Division is managed by the City Architect's office (CAO). The CAO supervises the
architectural design and construction of
facilities for the City of San Antonio, such as major downtown projects, fire and police stations,
libraries, parks and community facilities. Furthermore, CAO provides support to many City departments
in facility master planning and implementing their programs and space needs.
Pre-Design
-
Evaluate
departmental request
-
Site selection and
facility/site investigations
-
Develop facility space program
-
Develop preliminary project budget / estimate
-
Prepare Request for Qualification for
Architect/Engineer selection
-
Advertising for project
-
Assist in selection of potential
Architect/Engineer
-
Negotiate A/E scope and fees
-
Develop Contracts/Ordinances
-
Provides technical support, e.g., architectural, landscape architectural, engineering (geotechnical, GIS, MEP,
civil, structural, environmental, and
surveying)
-
Communicate between consultant and user
department for success
-
Provides project related information as
needed
Design
-
Standard Detail Drawings
-
Review consultant's program with user department.
-
Schematic discussion with Consultant.
-
Consult/assist with presentation to Historical Design Review Boards
and/or other public entities as needed.
-
Schedule preliminary design reviews with Development services.
-
Ensure environmental, historical, and archeological assessments.
-
Review submitted SD and recommends proceeding with Design Development.
-
Review/recommend consultant's invoice for payment.
-
Review Design Development and opinion of probable cost.
-
Recommend proceeding with Construction Documents (CD).
-
Review Documents for Construction.
Procurement
-
Advertising project for bids
-
Coordinates Pre-Bid conference
-
Evaluates Consultant's Review of bid
packages
-
Consultant makes recommendation
-
Assist in formalizing Ordinance and Contract
Construction
-
Pre-construction
conference/Issues notice to proceed
-
Coordinates with user when construction can
begin
-
Attends
construction meetings
-
Review
contractor's monthly pay applications
-
Assist user with any proposal requests
-
Review and approves GC's change orders
-
Approves Council change orders
-
Assist with punch list inspections
-
Assist
substantial & final completion
-
Assist with certificate of occupancy
-
Closeout project
-
Warranty period
-
Ensures file retention and library
management of all project related documents
|
|