Main Plaza today |
Design Principles |
Features & Vision |
Information Downloads
On December 6, 2005, the City released a Request for Qualification (RFQ)
for professional services in the redevelopment of Main Plaza. A committee
composed of representatives from the Downtown Alliance, and the departments of Parks and
Recreation, Asset Management, and Public Works reviewed and evaluated submittals.
The committee selected Bender Inc. dba/ Bender Wells Clark Design, which was the firm
that received the highest technical points and the most SBEDA (Small Business Economic
Development Advocacy) points.
In February 2006, City Council authorized compensation to Bender Wells
Clark Design for professional engineering basic services. Meanwhile, in
December 2006, City Council authorized the assignment of professional
design services to the sub-consultant, SWA Group.
Bexar County will fund a portion of the Main Plaza Redevelopment Project.
Construction on the Main Plaza project began in February 2007 and will be
substantially completed by April 2008. This schedule is dependent upon
favorable weather conditions, material availability, and other factors.
The Main Plaza approved budget comprised of all funding contributions is
$12.2 million. All funding to date has been approved by City Council.
This project will be a continuation of City Council policy to support
the adopted Downtown Master Plan, the Downtown Neighborhood Plan, and
the Historical Civic Center Master Plan.
|