                     Main Plaza Redevelopment
   
                        





Construction Timeline

February 28, 2007  
Phase I begins including construction of water, sewer, gas, and drainage related improvements.

A total street closure of Dwyer Street, from Market to the Dolorosa alleyway until July 23, 2007. Varying lane closures on Dwyer from Villita to Dolorosa. Lane closures along the Dolorosa alleyway and along Villita from Dwyer to the San Antonio River.
March 10, 2007  
Intersection of Market and Dwyer closes until April 5, 2007. At least two through traffic lanes on Market will be kept open during peak periods of traffic. Full intersection closure (when necessary) will be limited to nights and weekends.
April 30, 2007  
Permanent closure of Main Plaza Street. Permanent pavement marking, traffic signal timing, and signing will be implemented at Market/Dwyer intersection prior to reopening Dwyer south of Market.
May 3, 2007  
Lane closures of Commerce, Market, and Main Street until May 31, 2007. Partial lane closure on Commerce along the Main Plaza Street east of Main Street; partial lane closure on Dolorosa/Market adjacent to the Courthouse; and, partial lane closure on Main adjacent to the north portion of the Courthouse building.
June 1, 2007  
Permanent closure of Main Street. Partial single-lane closures may be required during this period. Permanent pavement marking, traffic signal timing, and signing will be implemented at Commerce/Main intersection.
June 2007-
     April 2008
 
Construction to include landscaping, fountains, stonework, etc. within Main Plaza to be completed during this period.
April 2008  
Main Plaza Project Substantially Complete
 


 


Services | Government | Business | Neighborhoods | Recreation
Home | Privacy Policy and Disclaimer | Text Only

Website best viewed using Microsoft Internet Explorer 6.0
with screen resolution settings of 800x600.