Traffic switched to southbound lanes (two way traffic maintained)
Completion of concrete column overlays southbound Harry Wurzbach Road
Poured concrete columns on northbound Harry Wurzbach Road
Installation of pre-cast concrete box culverts
Excavation for new ramp and retaining wall east of Harry Wurzbach
Earth reinforcement on east side of Harry Wurzbach Road
Continue excavation for new ramp and retaining wall on east side of Harry Wurzbach Road
Continue earth reinforcement on east side of Harry Wurzbach Road
Install new inlets
Begin tie in services for SAWS water lines
Remove concrete rails and sidewalk along Austin Highway
Pour new 8x10 concrete box culverts
Completed concrete columns Excavation for retaining wall and new ramp – North of Austin Highway
Completed concrete columns
Excavation for retaining wall and new ramp – North of Austin Highway
Excavation for retaining wall and new ramp – South of Austin Highway
Earth reinforcement in preparation for retaining wall and ramp
Box culvert installation
Download Harry Wurzbach at Austin Highway (SPUI) – Public Hearing Report 6-28-2018 (PDF)
Download Harry Wurzbach at Austin Highway (SPUI) – Public Hearing Presentation 5-8-2018 (PDF)
The City of San Antonio, in coordination with the Texas Department of Transportation, is working on a project to improve connectivity Harry Wurzbach and Austin Highway. This project includes the addition of four (4) connector ramps from between Harry Wurzbach and Austin Highway, transforming this intersection into a Single Point Urban Interchange (SPUI).
Harry Wurzbach & Austin Highway (SPUI) - Traffic Model
Anticipated Project Schedule (as of March 2019):
Schematic & Plan Design – Present to 01/2019 Advertisement & Construction – 01/2019 to 06/2021