All Work weather permitting.
Prepping Tezel/Timber Path for asphalt.
Prepping Tezel north of Timber Path for asphalt.
LIMITS
Culebra to Timber Path
SCOPE
Roadway reconstructed to five lanes, with bike lanes, drainage and traffic improvements from Culebra Road to Timber Path Road. CPS Energy and SAWS are also included within the project limits.
SCHEDULE
April 2015 to April 2016
Construction Cost
$3,965,384 CoSA Contract Value
$141,183 CPS Energy
$290,369 SAWS
$4,396,936 Total
TEAM
Transportation & Capital Improvements (TCI), City of San Antonio
SAWS
CPS Energy
San Antonio Constructors
Camacho-Hernandez & Associates, LLC