Transportation & Capital Improvements
Barbara Drive Drainage

Office

  • Physical Address
  • Municipal Plaza Building
    114 W. Commerce, 6th Floor
    San Antonio, TX 78205   
  • Mailing Address
  • P.O. Box 839966
    San Antonio, TX 78283-3966
  • Phone
  • 210.207.8022

Staff

  • Mike Frisbie, P.E.
    Director and City Engineer
  • Anthony Chukwudolue, P.E.
    Assistant Director
  • Razi Hosseini, P.E.
    Assistant Director
  • Christie Chapman
    Assistant Director
  • Arthur Reinhardt, P.E., C.F.M.
    Assistant Director
  • Nefi Garza, P.E.
    Assistant Director
  • Paul Berry
    Chief Communications Officer

Barbara Drive Drainage Project

*SPECIAL NOTICE*

The contractor will be closing Oblate between McCullough and Jones Maltsberger beginning Wednesday, June 20, 2018 thru Friday, June 22, 2018 from 9am to 3pm for underground utility locates. In the future, Oblate will be closed for utility relocation and installation of the new drainage system under the street. Advanced notification will be given when the dates of construction are determined. Please click here to view the detour map.

Project UPDATE MAY 2018

  • SAWS sewer has been completed
  • SAWS waterline on Basin at Shannon Lee has been completed
  • Basin street and concrete work continues
  • Continue excavation of the channel and demolition of box culverts

Channel at Basin & Skipper

Channel construction continues

Channel construction continues

Channel construction continues

Sidewalk along Shannon Lee

Sidewalk and curb at Basin & Shannon Lee

Sidewalk along Basin

First layer of asphalt and curb installation on Basin

 

 

If you have questions about the project, please contact:

 

Richard Casiano, Capital Projects Officer

210-207-8218, Richard.Casiano@sanantonio.gov

Visit us at
http://www.sanantonio.gov/TCI/Projects/BarbaraDriveDrainage.aspx

www.facebook.com/SanAntonioTCI

 

 

 

Transportation & Capital Improvements (TCI)
PO Box 839966
San Antonio, Texas 78283-3966
210-207-8022

 

 

The City of San Antonio and Bexar County are working on a collaborative effort to alleviate flooding in the Shearer Hills and Ridgeview neighborhoods located in Council District 1. Bexar County has performed preliminary engineering studies to analyze methods to reduce flooding in the area. 

In May 2013, this area experienced severe flooding, resulting in significant residential and commercial property damage. As a result, Bexar County revisited the preliminary design of this project and recommended an earthen channel between McCullough and Skipper as the first phase of a four phase project to alleviate flooding in the area. The first phase is anticipated to remove over 40 properties from the effective 1% annual chance (100-year) floodplain. Included in the first phase is the need to acquire approximately 35 residential properties along Barbara Drive and Shannon Lee based on the Bexar County preliminary earthen channel design. 

             

View the video of flooding from May 25, 2013 on YouTube.

The City of San Antonio and Bexar County agreed, approved by City Council on September 4, 2014, to collaborate funding for the project and for the City of San Antonio to oversee the design and construction of the project. 

The scope of project will consist of removing the existing concrete channel and underground box culvert drainage system east of McCullough Avenue and replacing the existing drainage system with a wider and deeper earthen channel to convey the 1% annual chance (100-year) ultimate design storm. 

PUBLIC MEETING PRESENTATION

View the public meeting presentation from 8-27-15.

View the public meeting presentation 4-28-2016

    Public Meeting Questions & Answers 4-28-2016

   Barbara Drainage Public Meeting Flyer 

View the public meeting presentation from 6-29-17.

Barbara Drainage one pager hand-out

Exhibit_PublicMtg2_01.pdf

DEMOLITION

  • Structure demolition is complete with the exception of one.
  • All remaining items such as fences will remain until construction. These will discourage vehicular traffic and help provide a barrier from the existing channel drop off condition.
DESIGN
  • 100% Design has been completed. 
  • Public pre-construction meeting held on June 29, 2017.

PROPERTY ACQUISITION

  • All but one of the properties within the project limits have been acquired by the City of San Antonio. However, the property owner is under contract and will be relocated within the next month.

APPEARANCES AND SAFETY

  • City forces will maintain lawns to keep a neat appearance and deter insects.

 CONSTRUCTION COST: $5M 1

  • 1 Construction Cost does not include Engineering, Environmental, or Real Estate Acquisition costs


Project is under construction (as of January 2018): 

Project Timeline (as of September 2014): 

  • Real Estate Acquisition Process: Estimate 18-24 months to complete 
  • Consultant Selection Process: Estimate 12 months to complete 
  • Obtain Contractor and Construct Project: Estimate 12-18 months to complete 
  • Total: 3-3.5 years

Approximately 35 properties along Barbara Drive and Shannon Lee will be purchased to complete this project. 

Affected property owners will be contacted by the City of San Antonio Transportation and Capital Improvements Department (TCI) Real Estate Team to share more information. For more information, please contact Steve Hodges (210-207-8234) or Hector Reynoso (210-207-8688). 

Residential Property owners within the project path may be eligible for the following payments: 

  1. Actual Moving and Related Expenses Payment 
    1. Actual moving and related expenses or 
    2. Fixed moving payment based on a Department of Transportation Moving Cost Schedule 
  2. Replacement Housing Payment
    Difference of the cost to acquire a comparable, decent, safe and sanitary replacement home and price paid for your home For Tenant/Occupants: Difference of the rent to be paid at a comparable, decent, safe and sanitary replacement home and current rent; and 
    1. Incidental expenses related to sale of home to City; and 
    2. Incidental expenses related to the purchase of replacement home; and 
    3. Interest rate differential (if applicable) 

Residents will also be provided with advisory services including referrals to social services, referrals to comparable housing, an explanation of assistance and timely notices. 

Notices will include: 

  • General Information Notice: Provided before any acquisition activity takes place, generally explains the benefits that you may be eligible to receive, and informs residents/owners of the project, the intent of the City o San Antonio to acquire the property, and cautions residents not to move prematurely 
  • Intent to Purchase: Written Offer to Acquire your Home 
  • Notice of Eligibility for Relocation Assistance: Informs you of the maximum amount of your replacement housing payment and fixed moving payment 
  • 90 Day Notice to Vacate: Displaced persons will be given at least 90 days to vacate their property; notice will indicate the earliest date on which your property is to be vacated 
  • 30 Day Notice to Vacate: Notice will have the exact date your property is to be vacated

Contact Us about Barbara DRive Drainage 

Pete Rodriguez 
Capital Projects Officer
City of San Antonio

210.207.8154
Steve Hodges 
Real Estate Manager
City of San Antonio

210.207.8234
Hector Reynoso 
Sr. Real Estate Specialist
City of San Antonio

210.207.8688

Sign Up for emails about Barbara Drive Drainage

Enter Email Address Go